The investments for the most significant projects of the medium-term investment plan for 2014-2016 are as follows:

INFRASTRUCTURE WORKS

  Description Project Budget
 
CONTAINER TERMINAL  
1
Construction of new sites for the storage of containers and total re-construction of the
floor surfaces at the Container Terminal (6th pier)
2,280,000 €
 
CONVENTIONAL PORT  
2
Construction of a new floor layer behind quay 24 of the 6th pier 1,200,000 €
3
Construction of a warehouse for special cargo at quay 24 (Buildings) 3,000,000 €
 
1st – 2nd PIER AREA  
4
Construction of a tourist shelter in the 1st – 2nd pier area 2,500,000 €
 
GENERAL INTEREST INFRASTRUCTURE  
5
THPA SA water & sewage network reconstruction works 2,238,000 €
6
Expansion and reconstruction of the Port of Thessaloniki railway network 1,200,000 €
 
TOTAL 12,418,000 €

ELECTRO-MECHANICAL EQUIPMENT – SUPPLIES

  Description Project Budget
7 Supply of a Container Bridge-Crane (Container Terminal) 6,500,000 €
8 Supply of 2 Front Lifts 10τν / 6+1 (Container Terminal) 320,000 €
9 Supply of Straddle Carriers (4pieces) 3,200,000 €
 
TOTAL CARGO TERMINAL
10,020,000 €
10 Supply of 2 power cranes for Quay 17 6,938,000 €
11 Supply of 2 power cranes for Quay 21 8,600,000 €
12 Supply of 2 Wagon Tows 595,000 €
13 Supply of 2 power cranes for the transportation of bulk cargo at quay 4 8,600,000 €
14 Solid Bulk Cargo Specialized Management Systems 4,000,000 €
 
TOTAL CONVENTIONAL PORT
28,733,000 €
16 Supply and installation of a contemporary ISPS system
for surveillance and access control
2,500,000 €
17 Implementation of single window - Port community system 500,000 €
18 Application of an Environmental Impact Study (EIS) 218,350 €
  TOTAL REMAINING EQUIPMENT 3,218,350 €
  TOTAL ELECTRO-MECHANICAL EQUIPMENT – SUPPLIES 41.971.350 €
  TOTAL BIG INVESTMENTS 2014-2016 54,389,350 €